Optimisation and distribution of manufactoring resources

Objectives

Success target

  • Break-down of operator’s work
  • Improved task distribution

Context

Busy warehouse with pallet trucks working

  • World’s second largest glass fibre production site
  • Very difficult social situation
  • Industry: Glass fibre production
  • Country: France
ActionsSkilled Workers
  • Listing of operator activities
  • Shop floor observation including timing of different tasks
  • Synthesis of results
  • Areas of improvement identified
  • Action plan recommended

Résults

graphique à baton + flèche

  • Analysis of 3 sectors
  • 3 action plans containing 300 points improvement